Completing quarterly claims

ADOPT Support Hub Logo

At the end of each quarter, project partners will have to complete and submit details of costs incurred over the quarter in order to claim their grant. Project facilitators should be able to provide support. The process will differ slightly depending on the project and type of partner organisation but below is an overview of the process.  

  1. Visit your project page on the IFS website 

  • Log on to the IFS funding portal and navigate to the appropriate project 

  • Only the designated Finance person from each partner organisation will be able to see and fill in the quarterly claim on the website 

  • Click on the Claims Button on the main project page. This screen shows historic claims that have been processed as well as the live, open claim. Click ‘Edit’ to open claim 

  • You have 30 days from the end of the quarter to make a claim 

 

  1. Costs table 

  • You will see a screen for the claim period which shows a table of all your project costs based on the forecast you submitted with the proposal. These are split into different categories e.g. labour, material etc. 

  • Go into each category and enter the amount that has been spent, and add a description e.g. labour for quarter 1. Documents will need to be provided as evidence e.g. timesheets, receipts for expenses, supplier invoices and can be uploaded in the relevant category section. 

  • Check the overheads – these may or may not be calculated automatically  

  • Note that InnovateUK grant funding is outside the scope of VAT, so all costs should be quoted without VAT e.g. Mileage HMRC rate of 45p/mile includes VAT so for mileage claims this needs to be removed 

  • If the actual cost is >10% higher or lower than forecast you will need to include a narrative of why that was in the relevant category section 

  • Note that for all expenditure, costs should not be claimed unless paid for.  You may have to provide evidence of defrayal if requested. 

  • Note that if you are claiming costs outside of period e.g. a supplier invoice received at end of period may not be paid until following period, please provide explanation for that to avoid claim being rejected. 

 

  1. Claim documentation 

  • This section only needs completing: 

  • If you didn’t add documents as evidence at the previous stage 

  • At end of project e.g. Independent Accountants Report; Project completion form. 

 

  1. Update forecast 

  • If any of the amounts you have entered for the quarter you are claiming for differ from what was originally forecast, you will need to update the forecast costs for subsequent quarters so the total project costs remain the same 

 

  1. Summary 

  • This will show you a summary of the claim. Check this is what you expected.  Add any additional notes that you think would be of use to explain progress of the project. 

 

  1. Submit the claim 

 

  1. Don’t panic if you are notified that the claim has been rejected – there will just be a query you’ll need to answer before it can be processed 

 

  1. Your MSP (monitoring service provider) will be able to assist with specific queries 

Test Solutions, Practices and Technologies with ADOPT

Got a great idea or approach to boost your farm’s productivity or sustainability? The ADOPT fund and innovation Support Hub are here to help you trial real solutions, get expert support, and access funding – all tailored for farmers, growers and foresters in England.

 

  • Test your ideas on-farm with practical, farmer-led research
  • Get funding – for application support (£2,500), and full project support (£50,000 - £100,000)
  • Work with experts & other farmers to turn ideas into action

 

Start your process and contact the Support Hub

Apply through Innovate UK